How Point-to-Point Relations Change Influence Lines in Schedule Networks

View/ Open
Metadata
Show full item record
Link to refer to this document:
Collections
Abstract
Influence line diagrams depict the effect of changing the duration of a single activity on the whole project’s duration. The behaviour of influence lines, transitions between criticality types were hitherto examined with certain limitations on the activities and the relations. Only the four end-point relationships were allowed, the finish-to-start, start-to-start, finish-to-finish, and the start-to-finish. This paper aims to extend the previous research by inspecting the influence lines and criticality types if not only these relations, but also point-to point relations are allowed.- Title
- How Point-to-Point Relations Change Influence Lines in Schedule Networks
- Author
- Lepel, Adrienn
- Hajdu, Miklós
- Date of issue
- 2022
- Access level
- Open access
- Copyright owner
- Szerző
- Conference title
- Creative Construction e-Conference 2022
- Conference place
- Online
- Conference date
- 9-11 July 2022
- Language
- en
- Page
- 222 - 232
- Subject
- CPM, Precedence Diagramming Method (PDM), Influence lines, Point-to-point relations
- Version
- Post print
- Identifiers
- DOI: 10.3311/CCC2022-029
- Title of the container document
- Proceedings of the Creative Construction e-Conference 2022
- ISBN, e-ISBN
- 978-615-5270-75-8
- Document type
- könyvfejezet
- Document genre
- Konferenciacikk
- University
- Budapest University of Technology and Economics
- Faculty
- Faculty of Architecture
- Department
- Építéstechnológia és Menedzsment Tanszék